HOME
GROUP BUSINESSES
REAL ESTATE
EPC
EPC PROJECTS
HOSPITALITY
HEALTHCARE
ABOUT NYATI GROUP
EPC CONTRACTING PROJECTS
ONGOING
COMPLETED
REAL ESTATE PROJECTS
ONGOING
RESIDENTIAL
COMMERCIAL
COMPLETED
RESIDENTIAL
COMMERCIAL
NYATI SWABHIMAN
NRI LOUNGE
OUR ESTEEMED CUSTOMERS
BLOG
IN THE NEWS
PRESS RELEASE
MEDIA COVERAGE
EVENT UPDATES
NYATI NEWSLETTER
TESTIMONIALS
DOWNLOADS
REGISTER WITH US
CUSTOMER PORTAL
EMPLOYEE PORTAL
CAREER
CONTACT US
MENU
SITE STATUS UPDATE
NYATI ELAN WEST III
SITE UPDATES AS ON DECEMBER 2021
Tower G5 - View Towards Elan West
Towers G5 & G6 _ View over JSPM College Ground
Towers G5 & G6 - Internal Gypsum & Painting In Progress
SITE UPDATES AS ON NOVEMBER 2021
G5 & G6 - RCC & Brickwork Complete
Parking Areas In Progress
SITE UPDATES AS ON OCTOBER 2021
G5 & G6 - Brickwork Complete
G5 & G6 - Gypsum in Progress
G5 & G6 - RCC Work Complete
SITE UPDATES AS ON AUGUST 2021
G5 & G6 - Brickwork Completed Till 11th Floor
G5 & G6 - View of Terrace Slab
RCC nearing completion
SITE UPDATES AS ON JULY 2021
Bldg G6 West III
G5 12 Slab Complited
G5 Bldg
G5 G6 Brick work done up to 10 th floor
G5 G6 West III
G5 G6 West III
West III G5 G6
SITE UPDATES AS ON MAY 2021
G5 & G6- RCC : 13th slab in progress
G5 & G6 - Brickwork : 10th floor in progress
G5 - Gypsum : 8th floor in progress, G6 - Gypsum : 9th floor in progress
G5 & G6- RCC : 13th slab in progress
G5 & G6 - Brickwork : 10th floor in progress
G5 - Gypsum : 8th floor in progress, G6 - Gypsum : 9th floor in progress
SITE UPDATES AS ON MARCH 2021
G-5 progressing 9th slab brick work completed till 6th floor
G-5 progressing 9th slab G-6 progressing 10th slab
G5 progressing 9th slab G6 progressing 10th slab
SITE UPDATES AS ON FEBRUARY 2021
Geneva G6 ( 9th slab completed & 4th floor Brick work completed) , Gardenia G5 ( 8th slab completed & 4th floor brick work completed )
Geneva G6 ( 9th slab completed & 4th floor Brick work completed) , Gardenia G5 ( 8th slab completed & 4th floor brick work completed )
Geneva G6 ( 9th slab completed & 4th floor Brick work completed) , Gardenia G5 ( 8th slab completed & 4th floor brick work completed )
Geneva G6 ( 9th slab completed & 4th floor Brick work completed) , Gardenia G5 ( 8th slab completed & 4th floor brick work completed )
Geneva G6 ( 9th slab completed & 4th floor Brick work completed) , Gardenia G5 ( 8th slab completed & 4th floor brick work completed )
Geneva G6 ( 9th slab completed & 4th floor Brick work completed) , Gardenia G5 ( 8th slab completed & 4th floor brick work completed )
SITE UPDATES AS ON JANUARY 2021
Geneva (G6- 6 sabs completed ) ,Gardenia (G5-5 salb completed)
Geneva (G6- 6 sabs completed ) ,Gardenia (G5-5 salb completed)
Geneva (G6- 6 sabs completed ) ,Gardenia (G5-5 salb completed)
Geneva (G6- 6 sabs completed ) ,Gardenia (G5-5 salb completed)
Geneva (G6- 6 sabs completed ) ,Gardenia (G5-5 salb completed)